To cap it all off…
Construction of the gigantic roof of the kindergarten building is in full swing…framing up, installing reinforcing iron and pouring concrete before the monsoon rains shut down construction in July. Most of the roofing materials are purchased apart from the cement.
On completion of the roof and after the monsoon rains, 2-3 rooms will be built concurrently as the budget allows till construction completed…with at least 4 rooms in use by April 2024.